Community Hospital-Fairfax to Build New Hospital
Construction of
the NEW Community Hospital-Fairfax 2008-2009
On July 18, 2008, shovels turned dirt from the construction site of our soon-to-be
new home. From that day on, the landscape on Highway 59 in Fairfax has been changing!
Read on for a month-by-month guide to our construction project.
December, 2009
December brought more than just snow at the construction site. Interior framing was installed for surgical and patient rooms and is almost complete. After the framing is done, drywall is scheduled to begin the last week of January. Other important steps, such as plumbing lines and the heating and air conditioning systems are currently being installed. The fire sprinkler system is complete. This month, department directors and supervisors took a tour of the facility. The group was the first to have lunch in what will eventually be the hospital’s cafeteria.
December Pictures
November, 2009
The interior is taking shape! Framing
for patient rooms can be seen in the inside of the new hospital. Also visible are
the overhead electrical, plumbing, HVAC and sprinkler system pipes and ducts. As
planned, window installment will be completed by the end of the month, allowing
for interior work to continue during the winter. Sealing off the outside means some
welcomed heating for the construction workers. Kiewit Construction Group reported
that during the year since the project began, there have been no accidents on the
construction for Kiewit Building Group or the subcontractors. Click on the link
below to view pictures of the hospital’s roof, which is near completion as
well as a picture of the interior’s progression.
November Pictures
October, 2009:
Construction of the exterior was a top priority this month. The end of the month
will bring the completion of the roof and window installation. After the exterior
is complete, approximately 52,000 square feet of concrete will be poured for the
interior floor.
October pictures
August/September 2009:
The exterior of the building began to take shape in late summer. During August and
September, 1,200 bricks were laid per day to create the exterior walls. A total
of 20,000 bricks were used to build the outside of the hospital.
August/September pictures
July, 2009:
The access roads and concrete for the parking lot were completed in July, as well
as the main entrance off of Highway 59. Many important steps were completed that
were not visible at the construction site. The architects framed a “mock up room”
where they set up furniture and equipment to lay out a visual of the future patient
rooms in the hospital. The purpose of this room was for the hospital staff to evaluate
the layout of furniture and equipment in an effort to better serve the patients.
Work on sewer and water lines began in mid-July. Man holes and underground concrete
work were completed as well.
July pictures
Spring 2009:
Fairfax boasted its very own “pyramid”
on the hillside in early 2009. This mound of dirt on the site was used to compact
the foundation where the hospital will be built. After the surcharge was cleared
away, a smoother, flatter area allowed us to envision the layout for the new facility.
Electrical lines and other necessary utilities connections were some of the first
changes seen at the site. During this time, the hospital staff worked many hours
with the architects to define the interior look of our new home.
Spring pictures